NRC Staff Should Stop Balking, Provide Fire Safety Information, Groups Say

 

Agency Is Refusing to Adhere to an Order to Release Document That Would Help Determine Safety of New Nuclear Reactors

 

WASHINGTON, D.C. – The Nuclear Regulatory Commission (NRC) should stop balking and provide a critical document that would reveal how the owners of a Texas nuclear plant expansion project plan to deal with a fire or explosion, three public interest groups told the commission late last week.

                                               

Three administrative judges of the Atomic Safety and Licensing Board have ordered the agency to provide at least a redacted version, but NRC staffers have refused. The NRC’s lack of transparency could impact the ability to get adequate safety-related information not only about the South Texas Project (STP) but about other proposed reactors around the country as well.

 

Late Friday, the groups – the Sustainable Energy and Economic Development (SEED) Coalition, Public Citizen and the South Texas Association for Responsible Energy – filed a brief with the NRC. It noted that the NRC staff’s refusal to provide the information violated President Barack Obama’s new transparency policy. The groups also said the NRC is acting arbitrarily and trying to shut the public out of NRC proceedings.

 

“After the Sept. 11 attacks, Congress required new fire and safety standards for all new plants and the NRC developed rules to reflect this. Now, the NRC is trying to do its work behind closed doors, and its staffers are literally making up how to handle information as they go along, keeping as much secret as possible,” said Karen Hadden, executive director of the SEED Coalition. “Without disclosure of this information, we can’t tell how well the NRC is doing in protecting the public.”

 

Friday’s filing was the latest in a regulatory battle that began in April 2009 when the three groups intervened in the licensing of two new reactors at the STP in Matagorda County in southeast Texas. The groups contend that the application for a license is inadequate.

 

The NRC has a new rule that requires licensees to develop and implement guidance and strategies to protect nuclear plants from explosions or fires, including those that would result from the crash of a large commercial airliner. By signing non-disclosure affidavits, the groups gained access to STP’s plan to comply with this rule and nuclear industry guidance on how to adhere to it.

 

On Aug. 14, the groups filed new “contentions” that STP was not adhering to the new fire safety rule.

 

Then, in October, the NRC posted on its Web site the existence of a draft document, referred to as ISG-016, which provides guidance to nuclear plant operators as to how to comply with the new fire safety rule. The NRC maintains that it is not a public document because it contains security-related information. The agency has created a new classification of document, called “sensitive unclassified non-safeguards information,” or SUNSI, and said that records in this classification, including ISG-016, are exempt from disclosure.

 

In November, the three public interest groups asked for the document but were turned down.

 

They appealed to the Atomic Safety and Licensing Board, which on Jan. 29 ordered the NRC staff to provide at least a redacted version of the document. In the order, three administrative judges chastised NRC staff for imposing unwarranted burdens on the groups and for misapplying procedures. Further, they noted that requirements to access the document should not be more stringent than the Freedom of Information Act and told the staff to go through the document, paragraph by paragraph, to identify the sensitive, non-public information, and provide the rest of the information to the groups.

 

The NRC appealed the order, which prompted Friday’s filing.

 

“It is crucial for the public to be able to participate in the licensing of new nuclear reactors that may be in its backyard,” said Tom “Smitty” Smith, director of Public Citizen’s Texas office. “We cannot meaningfully participate in the licensing of the STP reactors if we can’t get adequate safety information, and that includes whether these new reactors will be able to withstand a commercial jet crashing into them.”

 

Hadden noted that “the ability of the public to participate in licensing proceedings is particularly critical as the Obama administration is in the process of granting loan guarantees for new nuclear plants – the first to be built in the U.S. in decades.”

 

Last week, the administration announced an $8.3 billion loan guarantee for Southern Company to build two new reactors at its Vogtle plant in Georgia, and the administration has asked Congress to expand the program from $18.5 billion to $54 billion. The owners of the planned STP reactors – which include NRG Energy, Toshiba, CPS Energy – are seeking federal loan guarantees as well.

 

“The NRC wants to barrel along and license these plants with blinders on and without any involvement by the public,” Hadden said. “Well, the public has a right to be involved. People need to know what is being built in their communities and how safe it will be.”

 

A copy of the groups’ filing is available at http://nukefreetexas.org/downloads/intervenors_response_opposition_brief_ lbp_10_02.pdf.

 

 

The Atomic Safety and License Board order is at http://nukefreetexas.org/downloads/nrc_public_order_012910.pdf.

###

 

 

 

--
Eliza Brown
Clean Energy Advocate

Sustainable Energy & Economic Development (SEED) Coalition
1303 San Antonio #100
Austin, Texas 78701
512.637.9482 (office)


Permalink Tags:          
     Views: 2333 
Latest Blog Post by salon -Video- Somervell County Commissioners Court Special Sessions (2) Dec 23 2019
More Posts You Might Enjoy
Sheriff Logs, Jail Logs, Fire Logs from Nov 15, 2019 through Dec 18, 2019
Somervell County Hospital District CFO Report from Dec 5 2019 and I-35 Clinic Info
8/23/2019- Judgement Against The State of Texas and George Darrell Best
Audio-City of Glen Rose Town Council Meeting April 8 2019

 You! Leave a Comment! You Know you Want To!
You must be a registered member to comment on the blog.
Your first post is held pending approval to make sure you're not a spammer bot

 Not registered? Or you can login!

LOGON - Name:Password:

New poster comments are moderated, meaning they won't show up until approved... or not.  Be patient-we have lives outside this blog, so it might take awhile You want to be rude? totally stupid? inappropriate? Racist? Bigoted? Flame war baiter? Your post may be deleted. Spammers or people posting pretend interest comments but really wanting to hawk their latest book or sell stuff or govt propaganda flacks won't see their posts published. Comments do not necessarily reflect the viewpoint of the site owner(salon).
If you have a problem with logging in or registering, please speak up right away. Love your comments. Oh, except spammers
More on commenting



     

Click Here for Main Page



Guest
Today Is  
Saturday, January 18, 2020

Latest Posts


Paul Harper offered to settle State of Texas ex rel. Best v Harper lawsuit for $68k back in 2016
pharper 12/29/2019 Views 526



Video- Somervell County Commissioners Court Special Sessions (2) Dec 23 2019

salon 12/23/2019 Views 555



Top 100 Posts on Somervell County Salon for 2019

salon 12/22/2019 Views 369



Plans for Somervell County Salon Blog for 2020
salon 12/22/2019 Views 289



Imagine you were called up for jury duty and some people said they'd already made up their mind
salon 12/22/2019 Views 300



National Review on Removing Trump from Office (12/2019)
salon 12/22/2019 Views 291


More Blog Headlines








 



Comments

salon > Quick update on this, via Pacer-Click on pic to see larger (Turk Case Update- Telephone Conference Hearing Set for March 8 2019 )

salon > Lance Been awhile. Send me an email at salon@glenrose.net with the names of who you're talking about, above. Also, the newspaper editor is no longer local, ie officed here, but the paper is run.... (What Happened to Jerry Jacene? )

LanceHall > I'd love to see the Hotel Guest books and see if Jacene's name shows up long before he officially *found* the tracks.  I'd like to know if the Visitor's Bureau has emails wit.... (What Happened to Jerry Jacene? )

LanceHall > I see the land or that part of it is now in the hands of Glen Rose's own Corky Underwood. Is Jacene still involved?   I had already informed the Visitor Bureau manager (who's.... (What Happened to Jerry Jacene? )





Home | Blog Home | About | News | Piazza | Calendar | Audio/Video/Open Rec | Search
Write!  |profile | quotes |
top Daily | top Weekly |top Month | top Year | Top All! | archives | subscribe RSS